Cozy MKIV Builder's Log Book - May, 2002

DATE DESCRIPTION TIME

5/4/02
  1. Finish stick P.T.T. wiring - install both sticks
  2. Install canopy seal - adjust canopy latches - seal fuselage top
  3. Install elevators - rig elevator pushrods
  4. Install oil cooler & new gascolator
  5. Install propeller - safety wire bolts - do spinner after flight
  6. Test radio - some hum - try again when outside and further away
8 hrs
5/5/02
  1. Re-safety wire prop - torque to 40 ft-lb.
  2. Install I.P. labels
  3. Cut nose door to allow full swivel - NO CAN DO!
  4. Fill engine with oil - install oil filter
3 hrs
5/11/02
  1. Fab. gear legs heat shields - 1/8" aluminum
  2. Install gear leg heat shields
  3. Grease and install main whell bearings and wheels
  4. Trim vent lines
  5. Install strake gas drains and pitot tube
  6. Install gas cap retainers
  7. Clean up
5 hrs
5/12/02
  1. Polish canopy/windows scratches and spots
  2. Measure interior for upholstery - find auto upholsterer
3 hrs
------
PREVIOUS TOTAL: 2857 hrs MONTH TOTAL: 19 hrs
OVERALL TOTAL: 2876 hrs