Cozy MKIV Builder's Log Book - January 1995

DATE DESCRIPTION TIME

1/95 a) Order tools, etc. from Alexander Aero., Wicks, Aircraft Spruce (See P.O.'s)
1 hrs
1/95 a) Purchase work table and misc. parts from Somerville Lumber
2 hrs
1/95 a) Receive and unpack stuff
3 hrs
1/95 a) Build Epoxy Pump Warming Box
3 hrs
1/95 a) Build epoxy pump box, hot wire saw, finish table
b) Set up basement, set up pump
7 hrs
  START CHAPTER 4  
1/21/95 a) Begin cutting fuselage bulkheads
2 hrs
1/22/95 a) Continue cutting fuselage bulkheads
5 hrs
1/23/95 a) Continue cutting fuselage bulkheads
b) Order parts for Chapter 5
1 hrs
1/25/95 a) Continue cutting fuselage bulkheads
2 hrs
1/28/95 a) First bulkhead layup - Chapter 4
8 hrs
1/29/95 a) Trim yesterday's layups; cut glass for next layups
b) Trim and mount landing gear hard points
c) begin next round of bulkhead layups
9 hrs
1/30/95 a) Lay up 2nd side of SeatBack Bulkhead
2 hrs
------
PREVIOUS TOTAL: 27 hrs MONTH TOTAL: 44 hrs
CHAPTER 4: 28 hrs OVERALL TOTAL: 71 hrs